Fixed
Road surface in 51 Harlington Rd E, Feltham TW13 5BW.
Reported via desktop in the Pothole (minor) category anonymously at 05:26, Sun 16 May 2021
Sent to TfL 6 minutes later. TfL ref: FMS2728541.
I've complained about this before several times and still nothing is being done about it. The amount of potholes is getting absolutely ridiculous and as the trucks driver over the amount of noise is a joke. Myself and my neighbours have to put up with this day and night. So during the day I'm working from home and at night I can't sleep. TFL just keeps doing temporary repairs when the whole surface needs replacing. The noise from the sound of the trucks as they hit the potholes is so bad you can hear them travelling down the road even before you see them. I'm getting fed up with TFL on this and need it sorted. As explained on my previous complaints the vibrations are also causing my house to shake. It's never been this bad before and when I'm out my burglar alarm keeps going off as a result of this, and as a result we've had to move light fittings. I have a video of an example but cannot attach it a detailing this although it doesn't do it any justice as the noise is much louder in real time. You are welcome to call me to discuss. Direction of Travel: Northbound and Southbound.
Updates
-
Thank you for taking the time to report this to. We appreciate this an wanted to let you know that we’ve re-categorised this and it will now be directed to the appropriate team.
Category changed from ‘Pothole’ to ‘Pothole (minor)’
Posted by TfL at 05:31, Sun 16 May 2021
-
So basically the issue is between 51 Harlington Road East and all the way up to the pedestrian lights. There is a series of depressions in the road next to the pavement. As trucks go over these the noise generated is ridiculous. I have a video of one such example and if you send me an email address I can send it to you.
Posted anonymously at 21:08, Mon 17 May 2021
-
Sorry an update on the location. There are depressions in the road both on the side of and in the centre of the road surface from no. 61 Harlington Road East all the way up to the pedestrian crossing
Posted anonymously at 19:48, Tue 18 May 2021
-
Thank you for taking the time to report this to us. It is much appreciated. This will now be investigated by our team and we will aim to update on progress within 10 days. If the issue you have reported is an emergency, we will aim to update you on progress within 24 hours
State changed to: In progress
Posted by TfL at 16:18, Wed 19 May 2021
-
We have investigated this, and it has now been referred to our contractors. If the defect is confirmed as a safety issue, it will be made safe within 24 hours. A permanent repair, if needed will be carried out during our next programmed works for the area, or sooner if we can. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234
Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer
State changed to: Action scheduled
Posted by TfL at 12:24, Mon 24 May 2021
-
The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234
State changed to: Fixed
Posted by TfL at 05:32, Tue 22 June 2021
This report is now closed to updates from the public. You can make a new report in the same location.