Major Pothole Nuisance

Reported via desktop in the Pothole category anonymously at 21:33, Thu 10 June 2021

Sent to TfL less than a minute later. TfL ref: FMS2783795.

The pothole was reported last month to be levelled, but nothing was done and it is now reported as fixed - which it is not. Someone local has actually spraypainted the offending pothole for clarity (see photo). The pothole is creating a real nuisance for all the neighbouring properties as it is situated in a major bus/cycle lane. The buses thunder over it every 60 seconds causing major vibrations through all our properties. This is a major road with constant traffic, this MUST be fixed so we can actually get some undisturbed sleep. It has been steadily getting worse over the last 2 months. It is located outside 37 Tollington Road N7 6PB

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for taking the time to report this to us. It is much appreciated. We have investigated this, and it has now been referred to our contractors. If the defect is confirmed as a safety issue, it will be made safe within 24 hours. A permanent repair, if needed will be carried out during our next programmed works for the area, or sooner if we can. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234

    Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer

    State changed to: Action scheduled

    Posted by TfL at 21:36, Thu 10 June 2021

  • It has been 20 days, and the pothole still hasn't been fixed. It is still causing all the surrounding properties to violently shake every time a bus drives over it (every 60 seconds).

    Posted anonymously at 22:46, Tue 29 June 2021

  • The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234

    State changed to: Fixed

    Posted by TfL at 05:32, Fri 9 July 2021

This report is now closed to updates. You can make a new report in the same location.