Back to all reports

London Marathon fencing become loose and blown out into road

Reported via desktop in the Unstable hoardings category anonymously at 22:54, Thursday 30 September 2021

Sent to TfL less than a minute later. TfL ref: FMS3035074.

Two sections of the barrier for London Marathaon (that are joined together) have blown into the road, causing a hazard. It needs to be secured

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for taking the time to report this to us. It is much appreciated. This will now be investigated by our team and we will aim to update on progress within 10 days. If the issue you have reported is an emergency, we will aim to update you on progress within 24 hours

    State changed to: In progress

    Posted by TfL at 10:44, Friday 1 October 2021

  • Thank you for taking the time to report this to us. It is much appreciated. Your report has been investigated and we have referred it to the owner and have asked them to make this safe within 24 hours. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234

    Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer

    State changed to: Action scheduled

    Posted by TfL at 15:47, Friday 1 October 2021

  • The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234

    State changed to: Fixed

    Posted by TfL at 05:32, Saturday 30 October 2021

This report is now closed to updates. You can make a new report in the same location.