Fixed
London Marathon fencing become loose and blown out into road
Reported via desktop in the Unstable hoardings category anonymously at 22:54, Thu 30 September 2021
Sent to TfL less than a minute later. TfL ref: FMS3035074.
Two sections of the barrier for London Marathaon (that are joined together) have blown into the road, causing a hazard. It needs to be secured
Updates
-
Thank you for taking the time to report this to us. It is much appreciated. This will now be investigated by our team and we will aim to update on progress within 10 days. If the issue you have reported is an emergency, we will aim to update you on progress within 24 hours
State changed to: In progress
Posted by TfL at 10:44, Fri 1 October 2021
-
Thank you for taking the time to report this to us. It is much appreciated. Your report has been investigated and we have referred it to the owner and have asked them to make this safe within 24 hours. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234
Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer
State changed to: Action scheduled
Posted by TfL at 15:47, Fri 1 October 2021
-
The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234
State changed to: Fixed
Posted by TfL at 05:32, Sat 30 October 2021
This report is now closed to updates from the public. You can make a new report in the same location.