Entire lane coned off, no works
Reported via desktop in the Roadworks category anonymously at 14:07, Wed 8 December 2021
Sent to TfL less than a minute later. TfL ref: FMS3167494.
Entire lane on A312, the Parkway coned off for two consecutive days, including roundabout A312/A4. Huge traffic backlog, NO WORKS
Updates
-
Thank you for taking the time to report this to us. It is much appreciated. This will now be investigated by our team and we will aim to update on progress within 10 days. If the issue you have reported is an emergency, we will aim to update you on progress within 24 hours
State changed to: In progress
Posted by TfL at 07:54, Thu 9 December 2021
-
Thank you for taking the time to report this to us. It is much appreciated. This will now be investigated by our team and we will aim to update on progress within 10 days. If the issue you have reported is an emergency, we will aim to update you on progress within 24 hours
Posted by TfL at 07:54, Thu 9 December 2021
-
Thank you for taking the time to report this to us. It is much appreciated. So the issue with these planned works by Cadent Gas is that there initial proposals required a temp walkway within the carriageway due to a footway excavation. And a result of the road being a 50mph street we required an extensive amount of traffic management.
When the works got underway, Cadent contractors tried maintaining the footway via footboards. Therefore the travelling public were lead to believe the TM was no longer necessary. Unfortunately the footpath is shared use one between cyclists and pedestrians and a minimum of 2m could not be maintained. Our inspections team spotted this and reported back to us. Therefore we had to keep the lane closure in place for a temp walkway.
The works were finally completed yesterday by 20.00pm. We apologise for the inconvenience caused.
State changed to: Fixed
Posted by TfL at 12:06, Thu 9 December 2021