Fixed
The noise of the works
Reported via desktop in the Roadworks category anonymously at 00:41, Fri 25 February 2022
Sent to TfL less than a minute later. TfL ref: FMS3342420.
So this evening, Thursday 24/02/2022 - it's now 00.36 and I have tractors / JCB's / HGV lorries driving up and down the A2 slip road from the Sun & The Sands roundabout, this included a JCB using a jack hammer at 00.15 I understand these works need to take place, but do they really need to be during the week when I have a teenager doing mock exams for his GCSE's, a husband that has to be up for work at 06.30 and myself, who finds it extremely difficult to sleep with the noise, the amber flashing lights until a ridiculous time in the early hours of the morning?!? We had NO notification of these works being carried out, I cannot be the only resident that this is affecting?
Updates
-
Thank you for taking the time to report this to us. It is much appreciated. Our team had investigated this for you and found that this doesn't fall under the responsibility of Transport for London and comes under the remit of the local borough. You may therefore wish to report this issue by using www.fixmystreet.com, or directly to the borough. Should you need anything else, please contact our customer services team on 0343 222 1234
State changed to: not TfL’s responsibility
Posted by TfL at 09:23, Fri 25 February 2022
-
Thank you for taking the time to report this to us. It is much appreciated. We have since checked the area in question and carriageway resurfacing works were being out under the above permit number, the previous one you provided on your report was off our network. All works are now completed in the following areas, we would like to apologise for any inconvenience caused while the essential works were being carried out. Phase 1 and 2 - Lane 1 Closure S/B on Kidbrooke Park Road.
Phase 3- Lane 2 closure E/B on Shooters Hill Road, Lane 1 Closure N/B on Kidbrooke Park Road to be implemented.
Phase 4- Lane 2 closure E/B on Shooters Hill Road, Lane 1 Closure N/B on Kidbrooke Park Road to be implemented. Phase 1 & 2 - Directional Closure E/B of Shooters Hill Rd from Stratheden Rd to Sun in the Sands RAB, On and Offslip closures at RAB.
Phase 3- W/B Directional Closure of Shooters Hill Road near Sun in the Sands RAB to Stratheden Rd. On and Offslip closure at RAB. Shooters Hill Road slip closure.
Phase 4- W/B Directional Closure of Shooters Hill Rd near Sun in the Sands RAB to Stratheden Rd. On and Offslip closure at the RAB. Shooters Hill Road slip closure. Kidbrooke Park Rd Closure
State changed to: Fixed
Posted by TfL at 10:11, Fri 25 February 2022
This report is now closed to updates from the public. You can make a new report in the same location.