Fixed
Large pothole outside Green Man Community hub
Reported via mobile in the Pothole (minor) category anonymously at 11:15, Tue 25 April 2023
Sent to TfL 10 minutes later. TfL ref: FMS4483545.
This large pothole is in the road just before the traffic lights. It has caused considerable damage to my car as it is impossible to see - no markings around it.
Updates
-
Category changed from ‘Pothole’ to ‘Pothole (minor)’
Posted by TfL at 11:25, Tue 25 April 2023
-
This large pothole outside the Green Man Community Hub still has not been fixed and has caused substantial damage to my car! Both wheels on the nearside are damaged (front tyre damage and rim buckled, rear tyre split) and the suspension is rattling!
Posted anonymously at 10:52, Fri 28 April 2023
-
I was going home on monday night when my car found the pot hole it split my tyre that was only seven months old,i had to get a new tyre that was not cheap.
Posted by lyric de Silva at 13:22, Fri 28 April 2023
-
Thank you for taking the time to report this to us. It is much appreciated. This was investigated by our team and we were unable to find any defects, or issues at this location. This could be because it has already been resolved. However, if the problem remains, you either resubmit your report with some more information and a photo. Alternatively, you can contact our customer services team on 0343 222 1234 or by using this web form: https://tfl.gov.uk/ help-and-contact/ contact-us-about-streets-and-other-road-issues
State changed to: No further action
Posted by TfL at 10:40, Tue 2 May 2023
-
Thank you for taking the time to report this to us. It is much appreciated. We have investigated this, and it has now been referred to our contractors. If the defect is confirmed as a safety issue, it will be made safe within 24 hours. A permanent repair, if needed will be carried out during our next programmed works for the area, or sooner if we can. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234
Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer
State changed to: Action scheduled
Posted by TfL at 10:41, Tue 2 May 2023
-
Thank you for taking the time to report this to us. It is much appreciated. We have investigated this, and it has now been referred to our contractors. If the defect is confirmed as a safety issue, it will be made safe within 24 hours. A permanent repair, if needed will be carried out during our next programmed works for the area, or sooner if we can. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234
Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer
Posted by TfL at 10:41, Tue 2 May 2023
-
Any updates please?
Posted anonymously at 21:34, Mon 8 May 2023
-
The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234
State changed to: Fixed
Posted by TfL at 05:32, Wed 31 May 2023
This report is now closed to updates from the public. You can make a new report in the same location.