Major pothole in the middle of busy carriageway

Reported via mobile in the Pothole (minor) category anonymously at 17:34, Thu 3 August 2023

Sent to TfL 5 minutes later. TfL ref: FMS4856326.

There is a major pothole on the north circular roundabout near Hanger Lane that I have just hit. It has caused a puncture and possible damage to my vehicle underneath. The pothole is in the middle of the road and seems to have been reported on numerous occasions. This needs to be fixed before other vehicles or users get damaged. I also want someone to contact me regarding compensation for the incident.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Category changed from ‘Pothole’ to ‘Pothole (minor)’

    Posted by TfL at 17:39, Thu 3 August 2023

  • I have passed this onto our highways contractor to make safe. You will need to contact TfL customer services to make a claim.

    Posted by TfL at 08:37, Fri 4 August 2023

  • This was reported and attended to by our highways contractor.

    Posted by TfL at 09:04, Fri 18 August 2023

  • Thank you for taking the time to report this to us. It is much appreciated. We have investigated this, and it has now been referred to our contractors. If the defect is confirmed as a safety issue, it will be made safe within 24 hours. A permanent repair, if needed will be carried out during our next programmed works for the area, or sooner if we can. Should you need anything else or have any questions, you may wish to contact our customer services team on 0343 222 1234

    Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer

    State changed to: Action scheduled

    Posted by TfL at 08:49, Fri 25 August 2023

  • The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234

    State changed to: Fixed

    Posted by TfL at 05:32, Sat 23 September 2023

This report is now closed to updates from the public. You can make a new report in the same location.