Fixed
Lights out of phase
Reported via desktop in the General Fault category anonymously at 13:40, Fri 20 December 2024
Sent to TfL 2 days, 4 hours, 48 minutes later. TfL ref: FMS6885645.
All Tolworth roundabout traffic lights are out of phase at lunch time causing massive delays from all approaches. This is not a traffic volume problem it is a phasing one.
Updates
-
Thank you for taking the time to report this to. We appreciate this an wanted to let you know that we’ve re-categorised this and it will now be directed to the appropriate team.
Category changed from ‘General Fault’ to ‘Safety concern (traffic or pedestrian)’
Posted by TfL at 18:19, Sun 22 December 2024
-
Category changed from ‘Safety concern (traffic or pedestrian)’ to ‘General Fault’
Posted by TfL at 18:28, Sun 22 December 2024
-
Thank you for taking the time to report this to us. It is much appreciated. This has now been investigated and we can confirm that there is a non-urgent fault at these traffic lights. We have therefore referred it to our contractors, and you should see an improvement within 28 days. If you need anything else, or have any questions, please contact our customer services team on 0343 222 1234
Please also be aware that, all Action Scheduled reports are automatically closed after 28 days. However, the fault will be fixed within this timescale, which may be sooner, or in a few cases take a little longer.
State changed to: Action scheduled
Posted by TfL at 19:03, Fri 27 December 2024
-
The action scheduled for your report should now have been completed as detailed in your previous response. On some occasions it does take a little longer than scheduled. If you have any further queries on this, please either create a new report or contact our Customer Contact Centre on 0343 222 1234
State changed to: Fixed
Posted by TfL at 05:32, Saturday 25 January 2025
This report is now closed to updates from the public. You can make a new report in the same location.