Crazy traffic jam caused by road blocks but no road works.

Reported via mobile in the Roadworks category anonymously at 18:26, Tuesday 15 April 2025

Sent to TfL less than a minute later. TfL ref: FMS7440414.

There is no road works, but blocked lanes and crazy long/delayed temporary traffic lights cause miles long traffic jam. There is no visible reason these lanes should be closed and there's no visible reason there should be temporary traffic lights. It's a potential danger as well, as it's delaying emergency response time.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for taking the time to report this to us. It is much appreciated. This will now be investigated by our team and we will aim to update on progress within 10 days. If the issue you have reported is an emergency, we will aim to update you on progress within 24 hours

    State changed to: In progress

    Posted by TfL at 11:46, Tuesday 22 April 2025

  • Thank you for taking the time to report this to us. It is much appreciated. We had planned major UKPN works. The works were planned during school holidays and further mitigation with advance warning strategy and extensive stakeholder / resident / businesses consultation.

    The works were in its last phase where concrete was curing, which could explain the inactivity on site. UKPN returned on 16th April to complete reinstatement and clear site.

    If the issue persists, please raise another report or contact our customer services team on 0343 222 1234.

    State changed to: Fixed

    Posted by TfL at 12:12, Wednesday 23 April 2025

This report is now closed to updates from the public. You can make a new report in the same location.